Update 19th January 2018

Expansion Update

  • The foundations are nearing completion with the steel super-structure currently being erected.
  • The design and construction team met with Faculty Heads to confirm fixtures and fittings for the new classrooms and learning areas.
  • The next progress meeting has been moved to Tuesday 23rd January, after which we will be in a position to give more of an update.
  • Work is ongoing to create a link between the Music & Drama department and the front entrance (due for completion post-Easter break).
  • Work in ongoing on the extension to the staffroom (due for completion post-February break).

To view updated plans, please click here: Expansion Page